Image #1 (2.75" x 4.5"): "11-9-28. Building office in the Atlantic Coast Line R.R. Yard."; Image #2 (2.75" x 4.5"): "11-9-28. Erecting Span Traveler 'A' at and of West Approach, using 30 ton stiffleg derrick."; Image #3 (2.75" x 4.5"): "11-9-28. Raising boom for Span Traveler. Length of boom 100ft., & weight, 11 tons.";Three 4.5" x 2.75" B/W photos numbered 1, 2, 3
Image #4 (4.5" x 2.75"): "11-15-28. High Boom! Minimum reach with main falls is about 5 ft. Note the slack backstays. Weight of traveler complete = 122 tons, including 31 ton; 150 HP gas. engine on the upper deck and 60 HP aux. gas hoist on platform below."; Unnumbered Image (5" x 7"): "Span traveler A erecting on the Charleston or West Approach. Rear boom of traveler not yet erected.";One 4.5" x 2.75" B/W photo and one 5" x 7" B/W photo. Smaller photo numbered 4.
Image #5 (4.5" x 2.75"): "11-15-28. Front view of Span Traveler on the Charleston Approach."; Unnumbered Image (5" x 7"): "Erecting steel viaduct bent at 97 ft. reach.";One 4.5" x 2.75" B/W photo and one 5" x 7" B/W photo. Smaller photo numbered 5
Unnumbered Image (5" x 7"): "Unloading girders from R.R. cars and loading onto trucks on top of viaduct, to be pushed out to traveler by an 8 ton gasoline locomotive (extreme left.) Max-load handled = 97 ft. girder weighing 16 tons up 6% grade. Stiffleg derrick S.O. H383 - Capacity 30 tons. 70 ft. boom."; Image #6 (4.5" x 2.75"): "11-15-28. Rear view of Span Traveler on West Appr. 8 ton Vulcan gasoline locomotive in foreground.";One 4.5" x 2.75" B/W photo and one 5" x 7" B/W photo. Smaller photo numbered 6.
Images #8, 10, 12 (2.75" x 4.5"): Caption under all photos: Dec. 2, 1928. Three views of pneumatic caisson for anchor pier #10, Cooper River Span, which tilted to an angle 29 [degrees] from the vertical. Seven negro 'sand-hogs' trapped and drowned.";Three 4.5" x 2.75" B/W photos numbered 8, 10, 12
Image #13 (4.5" x 2.75"): "12-3-28. Span 10 W completed and erecting bent 8 W."; Image #15 (4.5" x 2.75"): "Charleston Viaduct completed to span 10 W. Looking west. 12-3-28."; Image #16 (4.5" x 2.75"): "12-3-28 Driving piles for false work footings under the west anchor arm of the Town Creek Span. Anchor Pier #1 in foreground. Main Pier #2 in background, elev. 134 ft.";Three 4.5" x 2.75" B/W photos numbered 13, 15, 16
Image #14 (2.75" x 4.5"): "12-4-28. Progress. Complete to span 9W."; Image #19 (2.75" x 4.5"): "12-13-29. Complete to 5W and erecting bent 3W."; Images #17, 18 (2.75" x 4.5"): "12-8-28. Wreck on West Approach after runaway of 14 ton girder which pushed locomotive down grade ahead of it.";Four 4.5" x 2.75" B/W photos numbered 14, 17, 18, 19