Image #289 (2.75" x 4.5"): "5-3-29. Erecting first bent of falsework at L2, East anchor arm."; Image #290 (2.75" x 4.5"): "5-3-29. Erecting first bottom chord of west anchor arm, Span 7, at Pier 7. Town Creek span in distance."; Image #292 (2.75" x 4.5"): "Same as 290.";Three 4.5" x 2.75" B/W photos numbered 289, 290, 292
Unnumbered Image (5" x 7"): "Progress in Cooper River, May 3, 1929 at 4:30 P.M. East Approach (right) complete except two spans.";One 5" x 7" B/W photo
Image #291 (4.5" x 2.75"): "5-3-29. East Approach nearing completion."; Image #294 (4.5" x 2.75"): "5-5-29. First panel of truss erected - west anchor arm."; Image #295 (4.5" x 2.75"): "5-6-29. Erecting first panel of floor - east anchor arm."; Image #297 (4.5" x 2.75"): "5-6-29. Progress in Cooper River.";Four 4.5" x 2.75" B/W photos numbered 291, 294, 295, 297
Image #298 (2.75" x 4.5"): "5-6-29. Our tank lighter and coal barge."; Image #299 (2.75" x 4.5"): "5-6-29. Traveler "B" moved out to L2. West anchor arm."; Image #300 (2.75" x 4.5"): "5-8-29. Second panel--west anchor arm complete. Traveler Bat L3, erecting portal bracing."; Image #301 (2.75" x 4.5"): "5-9-29. Traveler B erecting third falsework bent at L6, west anchor arm.";Four 4.5" x 2.75" B/W photos numbered 298, 299, 300, 301
Unnumbered Image (5" x 7"): "Airplane view of the Cooper River Bridge - looking east. May 9, 1929. West approach, in foreground, completely paved. Town Creek in foreground, then Drum Island, Cooper River, and Mt. Pleasant. Charleston in lower right.";One 5" x 7" B/W photo
Image #302 (2.75" x 4.5"): "5-9-29. Traveler B at L2, ready to move out to L3. East anchor arm."; Image #304 (2.75" x 4.5"): "5-9-29. Field office on bottom chord of deck span 10 - at anchor pier 10."; Image #305 (2.75" x 4.5"): "5-9-29. Looking west from traveler B toward traveler A. Town Creek span at left."; Image # 307 (2.75" x 4.5"): " 5-9-29. Erecting falsework bent at L6 - west anchor arm.";Four 4.5" x 2.75" B/W photos numbered 302, 304, 305, 307
Image #308 (2.75" x 4.5"): "5-9-29. Progress at noon."; Image #309 (2.75" x 4.5"): "5-9-29. Falsework bent #29, L6 - west anchor arm. Low tide, 25 ft. of water. 16 plumb piles & 8 batter piles under each column. Max. load = 20 1/2 tons per pile."; Image #310 (2.75" x 4.5"): "5-10-29. Traveler A, east side, at L4."; Image #311 (2.75" x 4.5"): " 5-10-29. Looking west from traveler on Cooper River Span, west anchor arm.";Four 4.5" x 2.75" B/W photos numbered 308, 309, 310, 311
Unnumbered Image (5" x 7"): "Progress in Cooper River, May 10, 1929, at 4:30 P.M. East viaduct (right) has been completed and viaduct traveler removed.";One 5" x 7" B/W photo
Image #312 (2.75" x 4.5"): "5-16-29. Progress in Cooper River."; Image #313 (2.75" x 4.5"): "5-16-29. West anchor arm - Span 7."; Image #314 (2.75" x 4.5"): "5-16-29. Looking east from traveler B on west anchor arm. Pier B in foreground, Elev. 132.0'."; Image #319 (2.75" x 4.5"): "5-16-29. Looking down on Span Traveler.";Four 4.5" X 2.75" B/W photos numbered 312, 313, 314, 319
Image #320 (2.75" x 4.5"): "5-17-29. Setting timber forms for concrete deck, East Approach."; Image #321 (4.5" x 2.75"); "5-17-29. Bowed plates in expansion joint at 9E on the East Approach. Taken to illustrate shop error. report made to V.B. & Iron Co."; Image #322 (2.75" x 4.5"): "5-17-29. Progress in Cooper River.";Three 4.5" X 2.75" B/W photos numbered 320, 321, 322